Microsoft Project Quiz – Microsoft Project Multiple Choice Questions and Answers: Dear aspirants, welcome to an informative new article. We have gathered the top and most frequently asked Microsoft Project multiple-choice questions and answers and compiled them here for you. To easily improve your logical and answering skills, practice these Microsoft Project MCQ questions and answers or take the Microsoft Project MCQ quiz. To ace your placement test or interview rounds, you must take a glance at the Microsoft Project quiz questions that are likely to be asked in various exams.
Microsoft Project Quiz
Before diving into the Microsoft Project Questions & Answers that are enclosed below, you guys first need to know a brief introduction about the Microsoft Project. Microsoft Project is a project management software developed and marketed by Microsoft. It is a powerful tool used to plan, track, and manage projects of any size and complexity. If you are preparing for a placement test or an interview, then having a good understanding of Microsoft Project can give you an edge over other candidates. To help you prepare effectively, we have compiled a list of Microsoft Project Multiple Choice Questions and answers that cover all the essential topics. By practicing these Microsoft Project MCQs, you can test your knowledge, identify your weak areas, and gain confidence in your ability to ace the exam.
Microsoft Project Quiz – Microsoft Project Multiple Choice Questions and Answers
Quiz Name | Microsoft Project Quiz |
Exam Type | MCQ (Multiple Choice Questions) |
Category | Technical Quiz |
Mode of Quiz | Online |
Top 125 Microsoft Project MCQs | Practice Microsoft Project Online Quiz
1. Which of the following describes Microsoft Project?
a) A word-processing software
b) A project management software
c) A graphics design software
d) A spreadsheet software
Answer: B
Explanation: Microsoft Project is a project management software developed by Microsoft. It is used to manage projects, create schedules, allocate resources, and track progress.
2. What file extension is used for Microsoft Project files?
a) .mpp
b) .docx
c) .xls
d) .pptx
Answer: A
Explanation: Microsoft Project files have a .mpp file extension.
3. What is a Gantt chart in Microsoft Project?
a) A chart that displays task dependencies
b) A chart that displays resource allocation
c) A chart that displays project milestones
d) A chart that displays the project schedule
Answer: D
Explanation: A Gantt chart in Microsoft Project is a chart that displays the project schedule.
4. What is a task in Microsoft Project?
a) An activity that must be completed to accomplish a project
b) A resource that is assigned to a project
c) A constraint that limits the start or end of a task
d) A summary of the project’s progress
Answer: A
Explanation: A task in Microsoft Project is an activity that must be completed to accomplish a project.
5. What is a resource in Microsoft Project?
a) An activity that must be completed to accomplish a project
b) A constraint that limits the start or end of a task
c) A summary of the project’s progress
d) A person, equipment, or material that is assigned to a project
Answer: D
Explanation: A resource in Microsoft Project is a person, equipment, or material that is assigned to a project.
6. What is a milestone in Microsoft Project?
a) A major event in the project
b) A task that can be completed quickly
c) A constraint that limits the start or end of a task
d) A summary of the project’s progress
Answer: A
Explanation: A milestone in Microsoft Project is a major event in the project, such as completing a phase or delivering a product.
7. What is a critical path in Microsoft Project?
a) The longest path through a project
b) The shortest path through a project
c) The path with the most resources assigned
d) The path with the least resources assigned
Answer: A
Explanation: The critical path in Microsoft Project is the longest path through a project, and it determines the shortest possible duration for the project.
8. What is a dependency in Microsoft Project?
a) A relationship between two tasks
b) A constraint that limits the start or end of a task
c) A resource that is assigned to a project
d) A summary of the project’s progress
Answer: A
Explanation: A dependency in Microsoft Project is a relationship between two tasks, indicating that one task cannot start until another task is completed)
9. What is a baseline in Microsoft Project?
a) The original project plan
b) The current status of the project
c) The expected final outcome of the project
d) The resources assigned to the project
Answer: A
Explanation: A baseline in Microsoft Project is the original project plan, which serves as a benchmark for measuring progress and performance.
10. What is the purpose of a network diagram in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: B
Explanation: The purpose of a network diagram in Microsoft Project is to display task dependencies, showing how tasks are related and which tasks must be completed before others can start.
11. What is a constraint in Microsoft Project?
a) A limitation on the start or end of a task
b) A resource that is assigned to a project
c) A summary of the project’s progress
d) A task that must be completed before others can start
Answer: A
Explanation: A constraint in Microsoft Project is a limitation on the start or end of a task, such as a specific date or a certain order of tasks.
12. What is the purpose of the Resource Sheet in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Resource Sheet in Microsoft Project is to display resource allocation, showing which resources are assigned to which tasks and for how long.
13. What is the purpose of the Task Form in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To enter and edit task information
Answer: D
Explanation: The purpose of the Task Form in Microsoft Project is to enter and edit task information, such as task names, durations, and dependencies.
14. What is the purpose of the Task Usage view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Task Usage view in Microsoft Project is to display resource allocation for each task, showing how much time each resource is assigned to each task.
15. What is the purpose of the Resource Usage view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Resource Usage view in Microsoft Project is to display resource allocation for each resource, showing how much time each resource is assigned to each task.
16. What is the purpose of the Critical Path Method (CPM) in Microsoft Project?
a) To determine the shortest possible duration for a project
b) To determine the longest possible duration for a project
c) To determine the amount of resources needed for a project
d) To determine the most efficient sequence of tasks for a project
Answer: A
Explanation: The purpose of the Critical Path Method (CPM) in Microsoft Project is to determine the shortest possible duration for a project by identifying the critical path, which is the longest path through the project.
17. What is the purpose of the Earned Value Analysis (EVA) in Microsoft Project?
a) To measure project progress and performance
b) To measure resource allocation and usage
c) To measure task dependencies and sequencing
d) To measure project risks and uncertainties
Answer: A
Explanation: The purpose of the Earned Value Analysis (EVA) in Microsoft Project is to measure project progress and performance by comparing the planned value, earned value, and actual cost of the project.
18. What is the purpose of the Resource Pool in Microsoft Project?
a) To manage and allocate resources across multiple projects
b) To manage and allocate resources within a single project
c) To display resource allocation for each task
d) To display resource allocation for each resource
Answer: A
Explanation: The purpose of the Resource Pool in Microsoft Project is to manage and allocate resources across multiple projects, allowing resources to be shared and reused)
19. What is the purpose of the Project Summary Task in Microsoft Project?
a) To summarize the entire project
b) To summarize each task within the project
c) To summarize the resources assigned to the project
d) To summarize the costs associated with the project
Answer: A
Explanation: The purpose of the Project Summary Task in Microsoft Project is to summarize the entire project, including the start and end dates, duration, and overall progress.
20. What is the purpose of the Gantt Chart view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: A
Explanation: The purpose of the Gantt Chart view in Microsoft Project is to display the project schedule, showing the start and end dates of each task and how they relate to each other.
21. Which of the following describes a Finish-to-Start (FS) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: A
Explanation: A Finish-to-Start (FS) task dependency in Microsoft Project means that the successor task cannot start until the predecessor task is completed)
22. Which of the following describes a Start-to-Start (SS) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: C
Explanation: A Start-to-Start (SS) task dependency in Microsoft Project means that the predecessor task cannot start until the successor task is completed)
23. Which of the following describes a Finish-to-Finish (FF) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: B
Explanation: A Finish-to-Finish (FF) task dependency in Microsoft Project means that the successor task cannot finish until the predecessor task is completed)
24. Which of the following describes a Start-to-Finish (SF) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: D
Explanation: A Start-to-Finish (SF) task dependency in Microsoft Project means that the predecessor task cannot finish until the successor task is completed)
25. Which of the following best describes a Project Calendar in Microsoft Project?
a) A calendar that shows the working hours and non-working days for a project
b) A calendar that shows the milestones and deadlines for a project
c) A calendar that shows the resources assigned to a project
d) A calendar that shows the costs associated with a project
Answer: A
Explanation: A Project Calendar in Microsoft Project is a calendar that shows the working hours and non-working days for a project, helping to define the project schedule and availability of resources.
26. Which of the following describes a Baseline in Microsoft Project?
a) A snapshot of the project schedule at a specific point in time
b) A list of resources and their availability for a project
c) A list of tasks and their dependencies for a project
d) A list of costs and expenses associated with a project
Answer: A
Explanation: A Baseline in Microsoft Project is a snapshot of the project schedule at a specific point in time, allowing the project manager to compare actual project progress with the original plan.
27. Which of the following is used to enter and manage project tasks in Microsoft Projects?
a) Task Form
b) Resource Sheet
c) Gantt Chart View
d) Task Usage View
Answer: A
Explanation: The Task Form in Microsoft Project is used to enter and manage project tasks, allowing users to specify task information such as name, duration, start and finish dates, and dependencies.
28. Which of the following is used to assign resources to tasks in Microsoft Project?
a) Resource Sheet
b) Task Form
c) Gantt Chart View
d) Resource Usage View
Answer: D
Explanation: The Resource Usage View in Microsoft Project is used to assign resources to tasks, allowing users to see how resources are being used and allocate them accordingly.
29. Which of the following is used to view resource availability and workload in Microsoft Project?
a) Resource Sheet
b) Task Form
c) Gantt Chart View
d) Resource Graph View
Answer: D
Explanation: The Resource Graph View in Microsoft Project is used to view resource availability and workload, showing users how resources are allocated across the project.
30. Which of the following is used to track actual project progress in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Resource Usage View
Answer: C
Explanation: The Task Usage View in Microsoft Project is used to track actual project progress, showing users how much work has been completed and how much work remains to be done.
31. Which of the following is used to view critical path analysis in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Resource Usage View
Answer: C
Explanation: The Network Diagram View in Microsoft Project is used to view critical path analysis, showing users which tasks are on the critical path and which can be delayed without impacting the project deadline.
32. Which of the following is used to view project costs and expenses in Microsoft Project?
a) Resource Sheet
b) Gantt Chart View
c) Task Usage View
d) Cost Table
Answer: D
Explanation: The Cost Table in Microsoft Project is used to view project costs and expenses, showing users how much money is being spent on resources and other project-related expenses.
33. Which of the following is used to view project milestones in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Milestone Report
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view project milestones, showing users when significant project events are scheduled to occur.
34. Which of the following is used to view project progress reports in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Report View
Answer: D
Explanation: The Report View in Microsoft Project is used to view project progress reports, providing users with an overview of project status and progress.
35. Which of the following is used to view project risks and issues in Microsoft Project?
a) Risk Register
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Risk Register in Microsoft Project is used to view project risks and issues, allowing users to identify and manage potential project problems.
36. Which of the following is used to create custom project views in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: C
Explanation: Custom Views in Microsoft Project are used to create custom project views, allowing users to tailor the software to their specific needs and requirements.
37. Which of the following is used to create custom project reports in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: D
Explanation: Custom Reports in Microsoft Project are used to create custom project reports, allowing users to generate and share project information in a variety of formats.
38. Which of the following is used to create custom data fields in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: A
Explanation: Custom Fields in Microsoft Project are used to create custom data fields, allowing users to track additional project information beyond what is provided by default.
39. Which of the following is used to customize the appearance of project views in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Themes
Answer: D
Explanation: Custom Themes in Microsoft Project is used to customize the appearance of project views, allowing users to apply a consistent look and feel across their project.
40. Which of the following is used to import and export project data in Microsoft Project?
a) Task Form
b) Import/Export Wizard
c) Gantt Chart View
d) Task Usage View
Answer: B
Explanation: The Import/Export Wizard in Microsoft Project is used to import and export project data, allowing users to share project information with other software applications or colleagues.
41. Which of the following is used to define project calendars in Microsoft Project?
a) Calendar Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Calendar Wizard in Microsoft Project is used to define project calendars, allowing users to specify working and non-working days and hours for the project.
42. Which of the following is used to adjust project schedules in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Resource Usage View
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to adjust project schedules, allowing users to modify task durations, start and finish dates, and dependencies.
43. Which of the following is used to track project expenses in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Cost Table in Microsoft Project is used to track project expenses, allowing users to monitor project costs and expenses and adjust budgets as needed)
44. Which of the following is used to manage project risks in Microsoft Project?
a) Risk Register
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Risk Register in Microsoft Project is used to manage project risks, allowing users to identify potential problems and take proactive measures to mitigate or prevent them.
45. Which of the following is used to view project task dependencies in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Task Usage View
Answer: C
Explanation: The Network Diagram View in Microsoft Project is used to view project task dependencies, allowing users to see how tasks are linked and which tasks must be completed before others can begin.
46. Which of the following is used to view project resource assignments in Microsoft Project?
a) Resource Sheet
b) Gantt Chart View
c) Resource Usage View
d) Task Usage View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to view project resource assignments, allowing users to see how resources are being used and allocate them accordingly.
47. Which of the following is used to view project progress and variances in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Tracking Gantt View
Answer: D
Explanation: The Tracking Gantt View in Microsoft Project is used to view project progress and variances, allowing users to see how the actual progress compares to the planned progress.
48. Which of the following is used to create recurring tasks in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Recurring Task Wizard
d) Task Usage View
Answer: C
Explanation: The Recurring Task Wizard in Microsoft Project is used to create recurring tasks, allowing users to set up tasks that occur on a regular schedule
49. Which of the following is used to manage project resources in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: A
Explanation: The Resource Sheet in Microsoft Project is used to manage project resources, allowing users to add, edit, and remove resources from the project.
50. Which of the following is used to adjust resource assignments in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Resource Usage View
d) Task Usage View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to adjust resource assignments, allowing users to modify the amount of time or effort that resources are allocated to specific tasks.
51. Which of the following is used to create project templates in Microsoft Project?
a) Template Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Template Wizard in Microsoft Project is used to create project templates, allowing users to save commonly used project settings, tasks, and resources as a template for future projects.
52. Which of the following is used to create project baselines in Microsoft Project?
a) Baseline Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to create project baselines, allowing users to save a snapshot of the project schedule and track progress against it.
53. Which of the following is used to track project issues in Microsoft Project?
a) Issue Log
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Issue Log in Microsoft Project is used to track project issues, allowing users to record and monitor problems that arise during the project and take appropriate action to resolve them.
54. Which of the following is used to view project costs in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Cost Table in Microsoft Project is used to view project costs, allowing users to see how much each task or resource is costing and identify areas where costs can be reduced)
55. Which of the following is used to define project constraints in Microsoft Project?
a) Constraint Form
b) Gantt Chart View
c) Task Usage View
d) Task Form
Answer: D
Explanation: The Task Form in Microsoft Project is used to define project constraints, allowing users to specify limitations on task start and finish dates.
56. Which of the following is used to create project scenarios in Microsoft Project?
a) Scenario Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Scenario Wizard in Microsoft Project is used to create project scenarios, allowing users to create and compare alternative project plans and determine the best course of action.
57. Which of the following is used to view project critical path in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view the project critical path, allowing users to see which tasks are critical to the project schedule and cannot be delayed without impacting the project’s completion date
58. Which of the following is used to view project resources by time period in Microsoft Project?
a) Resource Sheet
b) Resource Usage View
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Resource Usage View in Microsoft Project is used to view project resources by time period, allowing users to see how much time or effort each resource is allocated to specific tasks over the course of the project.
59. Which of the following is used to view project progress in Microsoft Project?
a) Progress Form
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view project progress, allowing users to see how much work has been completed and how much work is remaining for each task and for the project as a whole.
60. Which of the following is used to view project resource costs in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: A
Explanation: The Resource Sheet in Microsoft Project is used to view project resource costs, allowing users to see how much each resource is costing and identify areas where costs can be reduced)
61. Which of the following is used to view project tasks by resource in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Resource Usage View
d) Gantt Chart View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to view project tasks by resource, allowing users to see which tasks each resource is assigned to and how much time or effort they are allocated to each task.
62. Which of the following is used to view project work breakdown structure in Microsoft Project?
a) WBS Form
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The WBS (Work Breakdown Structure) Form in Microsoft Project is used to view the project work breakdown structure, allowing users to see the hierarchy of tasks and subtasks that make up the project.
63. Which of the following is used to view project costs by task in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: C
Explanation: The Task Usage View in Microsoft Project is used to view project costs by task, allowing users to see how much each task is costing and identify areas where costs can be reduced)
64. Which of the following describes Microsoft Project?
a) A word processing software
b) A project management software
c) A graphics design software
d) A spreadsheet software
Answer: B
Explanation: Microsoft Project is a project management software developed by Microsoft. It is used to manage projects, create schedules, allocate resources, and track progress
65. What file extension is used for Microsoft Project files?
a) .mpp
b) .docx
c) .xls
d) .pptx
Answer: A
Explanation: Microsoft Project files have a .mpp file extension.
66. What is a Gantt chart in Microsoft Project?
a) A chart that displays task dependencies
b) A chart that displays resource allocation
c) A chart that displays project milestones
d) A chart that displays project schedule
Answer: D
Explanation: A Gantt chart in Microsoft Project is a chart that displays the project schedule.
67. What is a task in Microsoft Project?
a) An activity that must be completed to accomplish a project
b) A resource that is assigned to a project
c) A constraint that limits the start or end of a task
d) A summary of the project’s progress
Answer: A
Explanation: A task in Microsoft Project is an activity that must be completed to accomplish a project.
68. What is a resource in Microsoft Project?
a) An activity that must be completed to accomplish a project
b) A constraint that limits the start or end of a task
c) A summary of the project’s progress
d) A person, equipment, or material that is assigned to a project
Answer: D
Explanation: A resource in Microsoft Project is a person, equipment, or material that is assigned to a project.
69. What is a milestone in Microsoft Project?
a) A major event in the project
b) A task that can be completed quickly
c) A constraint that limits the start or end of a task
d) A summary of the project’s progress
Answer: A
Explanation: A milestone in Microsoft Project is a major event in the project, such as completing a phase or delivering a product.
70. What is a critical path in Microsoft Project?
a) The longest path through a project
b) The shortest path through a project
c) The path with the most resources assigned
d) The path with the least resources assigned
Answer: A
Explanation: The critical path in Microsoft Project is the longest path through a project, and it determines the shortest possible duration for the project.
71. What is a dependency in Microsoft Project?
a) A relationship between two tasks
b) A constraint that limits the start or end of a task
c) A resource that is assigned to a project
d) A summary of the project’s progress
Answer: A
Explanation: A dependency in Microsoft Project is a relationship between two tasks, indicating that one task cannot start until another task is completed)
72. What is a baseline in Microsoft Project?
a) The original project plan
b) The current status of the project
c) The expected final outcome of the project
d) The resources assigned to the project
Answer: A
Explanation: A baseline in Microsoft Project is the original project plan, which serves as a benchmark for measuring progress and performance.
73. What is the purpose of a network diagram in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: B
Explanation: The purpose of a network diagram in Microsoft Project is to display task dependencies, showing how tasks are related and which tasks must be completed before others can start.
74. What is a constraint in Microsoft Project?
a) A limitation on the start or end of a task
b) A resource that is assigned to a project
c) A summary of the project’s progress
d) A task that must be completed before others can start
Answer: A
Explanation: A constraint in Microsoft Project is a limitation on the start or end of a task, such as a specific date or a certain order of tasks.
75. What is the purpose of the Resource Sheet in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Resource Sheet in Microsoft Project is to display resource allocation, showing which resources are assigned to which tasks and for how long.
76. What is the purpose of the Task Form in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To enter and edit task information
Answer: D
Explanation: The purpose of the Task Form in Microsoft Project is to enter and edit task information, such as task names, durations, and dependencies.
77. What is the purpose of the Task Usage view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Task Usage view in Microsoft Project is to display resource allocation for each task, showing how much time each resource is assigned to each task.
78. What is the purpose of the Resource Usage view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: C
Explanation: The purpose of the Resource Usage view in Microsoft Project is to display resource allocation for each resource, showing how much time each resource is assigned to each task.
79. What is the purpose of the Critical Path Method (CPM) in Microsoft Project?
a) To determine the shortest possible duration for a project
b) To determine the longest possible duration for a project
c) To determine the amount of resources needed for a project
d) To determine the most efficient sequence of tasks for a project
Answer: A
Explanation: The purpose of the Critical Path Method (CPM) in Microsoft Project is to determine the shortest possible duration for a project by identifying the critical path, which is the longest path through the project.
80. What is the purpose of the Earned Value Analysis (EVA) in Microsoft Project?
a) To measure project progress and performance
b) To measure resource allocation and usage
c) To measure task dependencies and sequencing
d) To measure project risks and uncertainties
Answer: A
Explanation: The purpose of the Earned Value Analysis (EVA) in Microsoft Project is to measure project progress and performance by comparing the planned value, earned value, and actual cost of the project.
81. What is the purpose of the Resource Pool in Microsoft Project?
a) To manage and allocate resources across multiple projects
b) To manage and allocate resources within a single project
c) To display resource allocation for each task
d) To display resource allocation for each resource
Answer: A
Explanation: The purpose of the Resource Pool in Microsoft Project is to manage and allocate resources across multiple projects, allowing resources to be shared and reused)
82. What is the purpose of the Project Summary Task in Microsoft Project?
a) To summarize the entire project
b) To summarize each task within the project
c) To summarize the resources assigned to the project
d) To summarize the costs associated with the project
Answer: A
Explanation: The purpose of the Project Summary Task in Microsoft Project is to summarize the entire project, including the start and end dates, duration, and overall progress.
83. What is the purpose of the Gantt Chart view in Microsoft Project?
a) To display the project schedule
b) To display task dependencies
c) To display resource allocation
d) To display project milestones
Answer: A
Explanation: The purpose of the Gantt Chart view in Microsoft Project is to display the project schedule, showing the start and end dates of each task and how they relate to each other.
84. Which of the following describes a Finish-to-Start (FS) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: A
Explanation: A Finish-to-Start (FS) task dependency in Microsoft Project means that the successor task cannot start until the predecessor task is completed)
85. Which of the following describes a Start-to-Start (SS) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: C
Explanation: A Start-to-Start (SS) task dependency in Microsoft Project means that the predecessor task cannot start until the successor task is completed)
86. Which of the following describes a Finish-to-Finish (FF) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: B
Explanation: A Finish-to-Finish (FF) task dependency in Microsoft Project means that the successor task cannot finish until the predecessor task is completed)
87. Which of the following describes a Start-to-Finish (SF) task dependency in Microsoft Project?
a) The successor task cannot start until the predecessor task is completed
b) The successor task cannot finish until the predecessor task is completed
c) The predecessor task cannot start until the successor task is completed
d) The predecessor task cannot finish until the successor task is completed
Answer: D
Explanation: A Start-to-Finish (SF) task dependency in Microsoft Project means that the predecessor task cannot finish until the successor task is completed)
88. Which of the following best describes a Project Calendar in Microsoft Project?
a) A calendar that shows the working hours and non-working days for a project
b) A calendar that shows the milestones and deadlines for a project
c) A calendar that shows the resources assigned to a project
d) A calendar that shows the costs associated with a project
Answer: A
Explanation: A Project Calendar in Microsoft Project is a calendar that shows the working hours and non-working days for a project, helping to define the project schedule and availability of resources.
89. Which of the following describes a Baseline in Microsoft Project?
a) A snapshot of the project schedule at a specific point in time
b) A list of resources and their availability for a project
c) A list of tasks and their dependencies for a project
d) A list of costs and expenses associated with a project
Answer: A
Explanation: A Baseline in Microsoft Project is a snapshot of the project schedule at a specific point in time, allowing the project manager to compare actual project progress with the original plan.
90. Which of the following is used to enter and manage project tasks in Microsoft Projects?
a) Task Form
b) Resource Sheet
c) Gantt Chart View
d) Task Usage View
Answer: A
Explanation: The Task Form in Microsoft Project is used to enter and manage project tasks, allowing users to specify task information such as name, duration, start and finish dates, and dependencies.
91. Which of the following is used to assign resources to tasks in Microsoft Project?
a) Resource Sheet
b) Task Form
c) Gantt Chart View
d) Resource Usage View
Answer: D
Explanation: The Resource Usage View in Microsoft Project is used to assign resources to tasks, allowing users to see how resources are being used and allocate them accordingly.
92. Which of the following is used to view resource availability and workload in Microsoft Project?
a) Resource Sheet
b) Task Form
c) Gantt Chart View
d) Resource Graph View
Answer: D
Explanation: The Resource Graph View in Microsoft Project is used to view resource availability and workload, showing users how resources are allocated across the project.
93. Which of the following is used to track actual project progress in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Resource Usage View
Answer: C
Explanation: The Task Usage View in Microsoft Project is used to track actual project progress, showing users how much work has been completed and how much work remains to be done.
94. Which of the following is used to view critical path analysis in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Resource Usage View
Answer: C
Explanation: The Network Diagram View in Microsoft Project is used to view critical path analysis, showing users which tasks are on the critical path and which can be delayed without impacting the project deadline.
95. Which of the following is used to view project costs and expenses in Microsoft Project?
a) Resource Sheet
b) Gantt Chart View
c) Task Usage View
d) Cost Table
Answer: D
Explanation: The Cost Table in Microsoft Project is used to view project costs and expenses, showing users how much money is being spent on resources and other project-related expenses.
96. Which of the following is used to view project milestones in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Milestone Report
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view project milestones, showing users when significant project events are scheduled to occur.
97. Which of the following is used to view project progress reports in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Report View
Answer: D
Explanation: The Report View in Microsoft Project is used to view project progress reports, providing users with an overview of project status and progress.
98. Which of the following is used to view project risks and issues in Microsoft Project?
a) Risk Register
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Risk Register in Microsoft Project is used to view project risks and issues, allowing users to identify and manage potential project problems.
99. Which of the following is used to create custom project views in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: C
Explanation: Custom Views in Microsoft Project are used to create custom project views, allowing users to tailor the software to their specific needs and requirements.
100. Which of the following is used to create custom project reports in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: D
Explanation: Custom Reports in Microsoft Project are used to create custom project reports, allowing users to generate and share project information in a variety of formats.
101. Which of the following is used to create custom data fields in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Reports
Answer: A
Explanation: Custom Fields in Microsoft Project are used to create custom data fields, allowing users to track additional project information beyond what is provided by default.
102. Which of the following is used to customize the appearance of project views in Microsoft Project?
a) Custom Fields
b) Custom Forms
c) Custom Views
d) Custom Themes
Answer: D
Explanation: Custom Themes in Microsoft Project are used to customize the appearance of project views, allowing users to apply a consistent look and feel across their project.
103. Which of the following is used to import and export project data in Microsoft Project?
a) Task Form
b) Import/Export Wizard
c) Gantt Chart View
d) Task Usage View
Answer: B
Explanation: The Import/Export Wizard in Microsoft Project is used to import and export project data, allowing users to share project information with other software applications or colleagues.
104. Which of the following is used to define project calendars in Microsoft Project?
a) Calendar Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Calendar Wizard in Microsoft Project is used to define project calendars, allowing users to specify working and non-working days and hours for the project.
105. Which of the following is used to adjust project schedules in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Resource Usage View
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to adjust project schedules, allowing users to modify task durations, start and finish dates, and dependencies.
106. Which of the following is used to track project expenses in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Cost Table in Microsoft Project is used to track project expenses, allowing users to monitor project costs and expenses and adjust budgets as needed)
107. Which of the following is used to manage project risks in Microsoft Project?
a) Risk Register
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Risk Register in Microsoft Project is used to manage project risks, allowing users to identify potential problems and take proactive measures to mitigate or prevent them.
108. Which of the following is used to view project task dependencies in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Task Usage View
Answer: C
Explanation: The Network Diagram View in Microsoft Project is used to view project task dependencies, allowing users to see how tasks are linked and which tasks must be completed before others can begin.
109. Which of the following is used to view project resource assignments in Microsoft Project?
a) Resource Sheet
b) Gantt Chart View
c) Resource Usage View
d) Task Usage View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to view project resource assignments, allowing users to see how resources are being used and allocate them accordingly.
110. Which of the following is used to view project progress and variances in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Task Usage View
d) Tracking Gantt View
Answer: D
Explanation: The Tracking Gantt View in Microsoft Project is used to view project progress and variances, allowing users to see how the actual progress compares to the planned progress.
111. Which of the following is used to create recurring tasks in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Recurring Task Wizard
d) Task Usage View
Answer: C
Explanation: The Recurring Task Wizard in Microsoft Project is used to create recurring tasks, allowing users to set up tasks that occur on a regular schedule.
112. Which of the following is used to manage project resources in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: A
Explanation: The Resource Sheet in Microsoft Project is used to manage project resources, allowing users to add, edit, and remove resources from the project.
113. Which of the following is used to adjust resource assignments in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Resource Usage View
d) Task Usage View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to adjust resource assignments, allowing users to modify the amount of time or effort that resources are allocated to specific tasks.
114. Which of the following is used to create project templates in Microsoft Project?
a) Template Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Template Wizard in Microsoft Project is used to create project templates, allowing users to save commonly used project settings, tasks, and resources as a template for future projects.
115. Which of the following is used to create project baselines in Microsoft Project?
a) Baseline Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to create project baselines, allowing users to save a snapshot of the project schedule and track progress against it.
116. Which of the following is used to track project issues in Microsoft Project?
a) Issue Log
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Issue Log in Microsoft Project is used to track project issues, allowing users to record and monitor problems that arise during the project and take appropriate action to resolve them.
117. Which of the following is used to view project costs in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Cost Table in Microsoft Project is used to view project costs, allowing users to see how much each task or resource is costing and identify areas where costs can be reduced)
118. Which of the following is used to define project constraints in Microsoft Project?
a) Constraint Form
b) Gantt Chart View
c) Task Usage View
d) Task Form
Answer: D
Explanation: The Task Form in Microsoft Project is used to define project constraints, allowing users to specify limitations on task start and finish dates.
119. Which of the following is used to create project scenarios in Microsoft Project?
a) Scenario Wizard
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The Scenario Wizard in Microsoft Project is used to create project scenarios, allowing users to create and compare alternative project plans and determine the best course of action.
120. Which of the following is used to view project critical path in Microsoft Project?
a) Task Form
b) Gantt Chart View
c) Network Diagram View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view the project critical path, allowing users to see which tasks are critical to the project schedule and cannot be delayed without impacting the project’s completion date.
121. Which of the following is used to view project resources by time period in Microsoft Project?
a) Resource Sheet
b) Resource Usage View
c) Task Usage View
d) Gantt Chart View
Answer: B
Explanation: The Resource Usage View in Microsoft Project is used to view project resources by time period, allowing users to see how much time or effort each resource is allocated to specific tasks over the course of the project.
122. Which of the following is used to view project progress in Microsoft Project?
a) Progress Form
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: B
Explanation: The Gantt Chart View in Microsoft Project is used to view project progress, allowing users to see how much work has been completed and how much work is remaining for each task and for the project as a whole.
123. Which of the following is used to view project resource costs in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Task Usage View
d) Gantt Chart View
Answer: A
Explanation: The Resource Sheet in Microsoft Project is used to view project resource costs, allowing users to see how much each resource is costing and identify areas where costs can be reduced)
124. Which of the following is used to view project tasks by resource in Microsoft Project?
a) Resource Sheet
b) Cost Table
c) Resource Usage View
d) Gantt Chart View
Answer: C
Explanation: The Resource Usage View in Microsoft Project is used to view project tasks by resource, allowing users to see which tasks each resource is assigned to and how much time or effort they are allocated to each task.
125. Which of the following is used to view project work breakdown structure in Microsoft Project?
a) WBS Form
b) Gantt Chart View
c) Task Usage View
d) Resource Sheet
Answer: A
Explanation: The WBS (Work Breakdown Structure) Form in Microsoft Project is used to view the project work breakdown structure, allowing users to see the hierarchy of tasks and subtasks that make up the project.
Microsoft Project MCQS and Answers offer a comprehensive and challenging platform for anyone looking to improve their knowledge and skills in using this project management tool. By leveraging the Microsoft Project Questions & Answers provided, users can boost their proficiency and confidence in working with Microsoft Project. We advise you to check our Freshersnow updates daily for more Technical Quizzes.